The Capacity Investment Scheme Australia program is becoming an important part of the country's changing electricity system. As ageing coal-fired power stations retire and electricity demand changes, Australia needs new generation and storage capacity to maintain a reliable supply.
The Capacity Investment Scheme, commonly known as the CIS, aims to encourage private investment by providing long-term revenue underwriting for eligible renewable generation and clean dispatchable projects.
The Australian Government says the scheme aims to deliver an additional 40 GW of capacity by 2030, consisting of 26 GW of renewable generation and 14 GW of clean dispatchable capacity. The scheme also supports the government's target of 82 per cent renewable electricity by 2030.
For Australian businesses, however, the central question is straightforward: what could all this new capacity mean for electricity prices?
The answer requires looking beyond a simple assumption that more renewables automatically equal cheaper business electricity.
The Capacity Investment Scheme Australia program is a revenue-underwriting mechanism designed to encourage investment in new electricity infrastructure.
Rather than the government directly building renewable energy projects, eligible developers compete through tenders. Successful projects can receive a long-term Capacity Investment Scheme Agreement that provides greater revenue certainty.
This arrangement reduces some of the financial risk associated with developing large energy projects. Consequently, projects that may otherwise struggle to attract investment can have greater certainty around future revenue.
The scheme primarily supports two categories.
| Capacity type | Examples | Role in the electricity system |
| Renewable generation | Solar and wind | Produces lower-emissions electricity |
| Clean dispatchable capacity | Battery storage | Stores electricity and supplies it when required |
In July 2025, the government increased the overall CIS target from 32 GW to 40 GW. The current target includes 26 GW of renewable generation and 14 GW of clean dispatchable capacity by 2030.
Tender rounds are occurring across both the National Electricity Market and Western Australia's Wholesale Electricity Market.
The Capacity Investment Scheme Australia could affect business electricity costs through several interconnected parts of the market.
Importantly, the scheme does not establish the retail electricity price that businesses pay. Instead, its potential price effects occur largely through investment, wholesale market competition, generation availability and system reliability.
Wholesale electricity prices reflect the interaction between electricity supply and demand.
Therefore, increasing the amount of available generation can increase competition among generators. Renewable generators also have relatively low short-run operating costs because wind and sunlight do not carry the ongoing fuel costs associated with coal or gas.
When substantial renewable output enters the market, wholesale electricity prices can consequently fall during those periods.
The Australian Government states that placing downward pressure on electricity prices is one of the objectives of the CIS.
However, businesses should distinguish between wholesale electricity prices and the final price on an electricity bill.
The relationship between the Capacity Investment Scheme Australia and commercial electricity bills is more complicated than the wholesale market alone.
A typical business electricity bill can include several cost components.
| Cost component | What affects it? |
| Wholesale electricity | Generation supply, demand, weather and fuel prices |
| Network charges | Transmission and distribution infrastructure |
| Environmental costs | Renewable and environmental schemes |
| Retail costs | Retailer operating costs and margins |
| Demand charges | A site's peak electricity demand |
| Contract structure | Fixed, progressive purchasing, market-linked or other arrangements |
Therefore, falling wholesale prices do not necessarily translate immediately or proportionately into lower business electricity bills.
For example, a company that has already fixed its electricity price under a multi-year contract may not immediately benefit from falling wholesale market prices. Conversely, that contract may protect the company if wholesale prices rise.
This makes contract structure and procurement timing particularly important during periods of significant market change.
One of the most important features of the Capacity Investment Scheme Australia is its support for dispatchable capacity.
Solar and wind generation depend on weather conditions. Solar output, for example, is strongest during daylight hours and disappears after sunset. Wind generation can also fluctuate significantly.
Battery energy storage can help manage these variations.
A battery can charge when electricity is abundant and discharge when the system needs additional supply. As a result, storage can help shift renewable electricity from periods of high generation into periods of higher demand.
For businesses, greater storage capacity could help reduce the severity of some wholesale price spikes and strengthen electricity reliability.
AEMO's planning also identifies renewable generation connected by transmission and distribution, firmed with storage and backed by gas as the least-cost development pathway under its current modelling for the National Electricity Market.
Nevertheless, actual business electricity costs will depend on how generation, storage, transmission and demand develop together.
Potentially, although electricity market volatility will not disappear.
One reason for expanding generation and storage is to support reliability as ageing coal-fired generators leave the system. AEMO has noted that future reliability depends on expected generation, storage and transmission investments being delivered on time and in full.
Additional renewable supply can create very low wholesale prices during periods of strong solar or wind generation. However, prices can rise rapidly when renewable production falls and demand remains high.
Storage can moderate this imbalance by moving electricity between periods.
Consequently, the future electricity market could experience more periods of low wholesale prices alongside occasional periods of scarcity and higher prices. The commercial effect will depend heavily on how individual businesses buy electricity.
The Capacity Investment Scheme Australia strengthens the case for businesses to think strategically about electricity procurement.
A changing generation mix can create both risks and opportunities. Therefore, simply renewing the same contract structure every few years may not provide the best fit for every organisation.
Businesses should monitor wholesale and forward electricity markets well before their existing contracts expire.
Waiting until the final months of a contract can reduce flexibility. Starting earlier provides more time to assess market movements and compare available offers.
Fixed-price contracts provide budget certainty but can limit the immediate benefit of falling wholesale prices.
Market-linked arrangements provide greater exposure to wholesale movements. However, they also expose businesses to periods of higher prices.
Hybrid or progressive procurement strategies can sometimes distribute purchasing decisions across different periods instead of committing the entire requirement at one market point.
The appropriate structure depends on consumption, financial objectives and tolerance for energy-market risk.
More renewable projects entering the electricity system may also create opportunities for businesses considering renewable energy procurement.
Depending on the organisation, options can include renewable electricity retail contracts, GreenPower, renewable energy certificates and Power Purchase Agreements.
However, businesses should assess pricing, volume commitments, contract duration and risk rather than selecting a renewable contract based solely on sustainability objectives.
The Capacity Investment Scheme Australia is national in scope, but electricity market conditions differ substantially across Australia.
The National Electricity Market covers Queensland, New South Wales, the Australian Capital Territory, Victoria, South Australia and Tasmania. Western Australia operates a separate Wholesale Electricity Market for its main south-west interconnected system.
Furthermore, electricity prices can differ between states and network areas because generation, transmission capacity, demand and local network charges vary.
Therefore, businesses with operations across multiple states should avoid treating electricity procurement as a single national pricing exercise.
Each site may have a different consumption profile, network tariff and market exposure.
The Capacity Investment Scheme does not require most electricity customers to take direct action. However, the scale of investment occurring across the electricity sector means businesses should regularly reassess their energy strategies.
Start by understanding your organisation's interval consumption data, peak demand and existing contract structure. Then examine contract expiry dates and begin reviewing procurement options well before renewal.
Businesses should also model different electricity price scenarios rather than relying on a single market forecast.
For example, compare the financial implications of wholesale prices falling, remaining relatively stable or increasing. This analysis can help determine how much price certainty the organisation requires.
Finally, consider energy efficiency, onsite solar, batteries, demand management and renewable procurement as parts of the broader strategy. Electricity procurement should not operate separately from how the business actually consumes energy.
The Capacity Investment Scheme Australia represents a significant change in the investment environment for Australia's electricity system.
Its targeted 40 GW of additional renewable generation and clean dispatchable capacity could substantially change the generation mix by 2030.
However, businesses should be careful about interpreting that target as a guarantee of a specific electricity price outcome.
Project construction schedules, transmission availability, coal generator retirement dates, weather, demand growth, gas prices and network investment will continue to influence electricity costs.
For commercial energy users, the key opportunity lies in becoming better prepared for those changing conditions.
An organisation that understands its consumption and has a clearly defined procurement strategy will generally be better positioned to respond to changing market conditions than one that waits until its electricity contract approaches expiry.
The Capacity Investment Scheme Australia is designed to accelerate investment in renewable electricity generation and clean dispatchable capacity while supporting reliability as Australia's electricity system changes.
For businesses, increased generation and storage could contribute to downward pressure on wholesale electricity prices and reduce some reliability risks. However, wholesale prices represent only one component of a commercial electricity bill. Network costs, contract structures, demand charges and procurement timing will remain important.
Therefore, businesses should focus on the factors they can control: understanding consumption, reviewing contracts early, comparing procurement structures and actively managing energy-market exposure.
Energy Action helps Australian organisations navigate electricity procurement, contract management and energy-market complexity. By combining market insights with structured procurement strategies, Energy Action can help your business evaluate its options as Australia's electricity system evolves. Visit Energy Action to explore how a more informed energy strategy could support better cost control and long-term planning.
The Capacity Investment Scheme Australia is an Australian Government revenue-underwriting program designed to encourage investment in renewable generation and clean dispatchable capacity. Developers compete through tenders, with successful projects receiving greater long-term revenue certainty. The scheme currently targets an additional 40 GW of capacity by 2030.
The scheme aims to place downward pressure on electricity prices by encouraging additional generation and storage investment. However, it does not guarantee lower electricity bills for individual businesses because wholesale electricity is only one part of the final cost. Network charges, environmental costs, retailer pricing, demand charges and individual contract structures also influence business electricity bills.
Battery storage can absorb electricity during periods of abundant generation and supply it back to the system when demand is higher. This flexibility can help manage renewable variability and potentially reduce the severity of some wholesale price spikes. Nevertheless, the final impact on an individual business depends on its electricity contract and consumption profile.
The Australian Government's current target is an additional 40 GW of capacity by 2030. This consists of 26 GW of renewable generation and 14 GW of clean dispatchable capacity. The government increased the target from 32 GW to 40 GW in July 2025.
Businesses can start by reviewing electricity consumption, demand patterns, contract expiry dates and current procurement arrangements. They should also monitor market conditions and compare fixed, market-linked and other procurement structures rather than assuming one approach will always provide the lowest cost. Combining procurement with energy efficiency, demand management and renewable energy options can provide a more comprehensive approach to managing future energy costs.